What is the installation method of the calender
From:admin
Date:2023/5/25 10:55:36
Casting machine is used to produce cast film equipment, mainly in the packaging industry, after the purchase of the cast machine equipment needs to be installed on site, here to give you a brief introduction to do some related.
Scribe the horizontal and vertical center line on the base of the cast machine, put a wedge-shaped inclined iron near the hole of the foot bolt, then hoist the frame, and the foot bolt into the corresponding installation hole on the base, installed washers and nuts and other fasteners, a little loose.
Adjust carefully so that the pre-drawn center line on the base coincides with the center line of the foundation, and the allowable deviation is ±1mm. slightly tighten the foot bolt and adjust the adjustable pad iron so that the large plane of the frame and transmission device can reach the level.
Before the equipment, the roller should be cleaned to remove the anti-rust oil and other debris. The cleaning of roller journals can be cleaned with clean cotton yarn and No.120 rubber solvent oil. Lifting each roller. Lifting rollers to equipment clean rollers to start, for the cast roller, cooling roller, in turn, each roller and both bearings into the rack. When each roller is installed, should again check the level of the calender roller to see if it meets the requirements, check the height of the center line of the calender.
When the calender adopts rolling bearing, the level deviation of the base is less than 0.04mm/1000mm. in the process of leveling, the tightening degree of each foot bolt should be uniform, and the method of tightening and relaxing the foot bolt should not be used to find the level. If the use of non-adjustable wedge gasket, after finding the level, use spot welding to fix the gasket position.
Through the above introduction, I believe that we have understood it! In fact, the installation of the calender is still relatively important, directly affecting the late production of products.